Open / Close Advertisement

Primetals Technologies Completes Automation Upgrade of Shougang’s Hot Strip Mill No. 1

The companies said upgrades included the existing level 2 system and various level 1 functions for the reversing roughing stands, 6-strand finishing mill, the sizing press and the coilbox. Due to the modernization, a wider range of steel grades can be modeled with better accuracy. 

Features include modern press models, several customer-specific functions and refining of the mill’s cooling strategies. Primetals Technologies also installed a diagnostic plug for advanced analysis and diagnostics along with the contour and flatness optimizer. 

To prepare for the production ramp-up, the model was trained during a four-week shadow mode operation. Level 2 commissioning was then conducted over a scheduled 10-day annual maintenance shutdown. In five production days, the mill reached 90% of its average daily output; it took ten days for run at full capacity, the companies said.