08/14/2017 - India’s Rashtriya Ispat Nigam Ltd. (RINL) has completed a US$62.4 million overhaul of the No. 1 steel shop at its Visakhapatnam Steel Plant.
The company fired up the third of the steel shop’s three new converters this spring, marking the end of a project that will lift steel production nearly 17% to 3.5 million metric tons per year.
As part of the project, SMS group designed and built the core components of the 150-metric-ton vessels, which are outfitted with the company’s lamella suspension system and bottom-stirring equipment for combined blowing oxygen-lance systems.
In addition, the primary de-dusting system was upgraded and new secondary de-dusting systems were added. The gas cleaning system is designed as a wet dust-collection facility with venturi scrubber, SMS said.
SMS group also oversaw installation and commissioning.
“With SMS group we have a reliable partner by our side and this is especially important when handling highly complex modernization projects,” said Ponnapalli Madhusudan, chairman and managing director of Visakhapatnam Steel Plant.



.jpg?lang=en-US&ext=.jpg)
.gif?width=220&height=200&mediaprotectionhash=374c6b9a31f2b2fbfc7937391034efb46fd57feba997b9ad2ae9a0bd3d48329d&ext=.gif)

.gif?width=100&height=200&mediaprotectionhash=e2d5b15d68f84f22038524be6c58e5268d67b7f44494b544e29a8d53c5b959ba&ext=.gif)