L.B. Foster Supplies Steel Grid Decking for NYC Bridge
01/22/2010 - L.B. Foster Co. is supplying the City of New York DOT with 10,000 ft2 of steel grid decking to replace the roadway of the Greenpoint Avenue Bridge over Newtown Creek. The company will also provide 2500 ft2 of 7-ft-wide decking for the drawbridge's sidewalks.
L.B. Foster Co. is supplying the City of New York Department of Transportation with 10,000 ft2 of steel grid decking to replace the roadway of the Greenpoint Avenue Bridge over Newtown Creek.
L.B. Foster will also provide 2500 ft2 of 7-ft-wide decking for the drawbridge's sidewalks. The decking will be manufactured at the company's Fabricated Bridge Products facility in Bedford, Pa., and delivered ready to install with concrete precasted into the panels.
"The grid decking reinforces the precast concrete to form a composite material that takes advantage of the best properties of both the concrete and steel," said Mike Riley, Sales and Marketing Manager of L.B. Foster's Fabricated Bridge Products group.
This City of New York DOT bridge rehabilitation project is being funded with stimulus money from the American Recovery and Reinvestment Act. Judlau Contracting, Inc. of College Point, N.Y., is the project general contractor.
Deliveries are scheduled to begin in June 2010 and for completion by August 30, 2010.
L.B. Foster Co. of Pittsburgh, Pa., supplies transportation, construction, utility, recreation, and agriculture markets with the materials necessary to build and maintain North America's infrastructure. The Fabricated Bridge Products group of L.B. Foster has been a leading provider of structural steel, bridge decking, railing, and drainage systems for the construction and rehabilitation of the nation's bridges, highways, and buildings for more than 40 years.