09/12/2008 - Mechel OAO commissions a new long wall face equipped with a powered mining complex at the Olzherasskaya-Novaya Mine of its Southern Kuzbass OAO coal mining subsidiary.
Mechel OAO has commissioned a new long wall face at the Olzherasskaya-Novaya Mine of its Southern Kuzbass OAO coal mining subsidiary. Mechel invested approximately $100.0 million (RUR2.5 billion) in the mine's construction.
The new high productive long wall face No. 21-1-3 in seam 21 is equipped with a powered mining complex, manufactured by CODCO of China, using a special sub-level caving method, which enables thick seam mining in one coal layer of up to 10 meters. The powered mining complex equipment was reinstalled from the mined-out extraction pillar of the mine's long wall face No. 21-1-5.
"The Olzherasskaya-Novaya Mine, which is equipped with the most advanced and highly productive underground mining equipment, removed its first tonne of coal in September 2006 and first million tonnes of coal in May 2007,” commented Mechel Management OOO Chief Executive Officer Vladimir Polin.
The new long wall face's coal reserves will exceed 1.5 million tonnes, which will be worked on by the mine's extraction team for about one year. The monthly productivity of the long wall face will be 150,000 to 180,000 tonnes of coal.
“The mine's designed capacity, which is expected to be reached in 2010, will be 2.4 million tonnes per year," added Polin. “The commissioning of the new long wall face will increase mined volumes of GZhO (gas, fat, and meager) grade coal and will provide Mechel's Kuzbass Central Processing Plant with a high grade raw material.”